icon_corner icon_start_stop icon_start_stop icon_start_stop icon_post icon_miss icon_save icon_card_red icon_save icon_start_stop icon_sub icon_card_yellow accessibility icon account-off icon account-on icon arrow-left icon arrow-right icon attack icon chevron-down icon chevron-left icon chevron-right icon chevron-up icon Combined Shape Created with Sketch. cross icon defence icon icon_disallowed_goal email icon facebook icon giphy icon google icon instagram icon linkedin icon lock icon messenger icon padlock icon Svg Vector Icons : http://www.onlinewebfonts.com/icon Panel Created with Sketch. Pattern Created with Sketch. pinterest icon Icon_PlayButton Created with Sketch. plus-thin icon plus icon Created with Sketch. Created with Sketch. search icon soundcloud icon sub-in icon sub-out icon tweet icon twitter icon icon_user__out icon_user_out vimeo icon whatsapp icon icon_start_stop youtube icon

Club news

Gallery: New Canford training complex update

AFC Bournemouth AFC Bournemouth

A gallery of the latest developments at the club’s new training complex at Canford Magna.

The progress of the impressive new site continues with several key areas following the opening of the covered 4G pitch.

The concrete frame of the main building is on programme with completion due at end of March; the external façade is due to start in mid-March.

Furthermore, the pitch maintenance building’s steel frame is complete, including the roof and mezzanine level. Wall cladding and windows are expected to be installed by the end of April; an internal fit out will then follow.

Pitch construction is underway and all three first-team pitches are due for handover in June.

Circulation roads are well advanced, with works now progressing on car parks. A site-wide distribution of new major services are also being installed.

Flick through the above images to get the latest ground-level look at how things are progressing.